I Bank Funding Projects
Tank Paintings. Forest Hill Pump Station Replacement. Well 8 Rehab
Tank Paintings. Forest Hill Pump Station Replacement. Well 8 Rehab
Enclosing all current carbon vessels inside a structure to protect the vessels from the elements and ensure proper function.
Continuing our replacement program to replace all Transite water mains in the Township
Redeveloping an existing well each year to properly maintain our GPM’s for each well
Ensuring we continue to be non-detect for all substances by continuing our carbon vessel replacement project. Approximately one vessel changeout each year. To keep up with the new MCL’s for PFAS
Responsible for the replacement of galvanized services in the street and on private property. Approximately 2,500 properties need to inspected to confirm material of pipe.
Redevelopment to increase capacity to obtain 425 GPM. Sodium removal treatment facility on site for well 12 and 13. Separating well 12 and 13 to be treated individually.